We have been advised of the following planned maintenance work being carried out at the Bluesquare Milton Keynes data centre:
What
Lumison/Bluesquare will be carrying out routine maintenance on the UPS System that support the critical load on the B side of the Milton Keynes Data Centre
Each unit will be serviced individually and returned to the string before moving onto the next unit ensuring that your rack equipment will always have 1 backed up power supply throughout the exercise.
Why
In keeping with the manufacturers recommendations, and the
Lumison/Bluesquare Planned and Preventative Maintenance regime we carry out this exercise at the prescribed times to ensure that all of our Data Centre systems continue to deliver the performance expected in a critical environment.
This work forms a major part of this regime.
When
The work is now scheduled to take place on 4th March at 21:00 and is scheduled to last for 4 hours.
Should you have any questions or queries, please don’t hesitate to contact us via the ticket system at https://support.c4l.co.uk